Steel Truss Pedestrian Bridge
Construction cost estimate
Original Excel workbook containing the preliminary construction estimate and project cost assumptions.
Construction estimate workbook
| A | B | C | |
|---|---|---|---|
| 1 | STEEL TRUSS BRIDGE | COST ESTIMATE | ||
| 2 | Conceptual pedestrian bridge • Ontario • CAD • Preliminary allowances | ||
| 3 | |||
| 4 | Work package | Cost item | Estimated cost |
| 5 | Preconstruction | Survey and utility locating | $9,000.00 |
| 6 | Preconstruction | Geotechnical and environmental studies | $24,000.00 |
| 7 | Preconstruction | Engineering and approvals | $45,000.00 |
| 8 | Preconstruction | Permit and agency fees | $7,000.00 |
| 9 | Site works | Mobilization and site setup | $28,000.00 |
| 10 | Site works | Clearing and grading | $12,250.00 |
| 11 | Site works | Erosion and sediment controls | $12,000.00 |
| 12 | Site works | Excavation and backfill | $22,500.00 |
| 13 | Site works | Temporary access and dewatering | $18,000.00 |
| 14 | Substructure | Abutments and foundations | $170,000.00 |
| 15 | Substructure | Bearings and anchor assemblies | $18,000.00 |
| 16 | Substructure | Drainage and protection | $18,000.00 |
| 17 | Superstructure | Steel material and shop fabrication | $83,935.80 |
| 18 | Superstructure | Protective coating | $16,787.16 |
| 19 | Superstructure | Deck system | $32,400.00 |
| 20 | Superstructure | Pedestrian railing | $20,160.00 |
| 21 | Superstructure | Transport and delivery | $15,000.00 |
| 22 | Superstructure | Crane and erection | $35,000.00 |
| 23 | Finishing | Approach pathways and transitions | $40,000.00 |
| 24 | Finishing | Restoration and landscaping | $10,500.00 |
| 25 | Finishing | Signage and site amenities | $5,000.00 |
| 26 | QA and closeout | Inspection and testing | $15,000.00 |
| 27 | QA and closeout | Contract administration and closeout | $18,000.00 |
| 28 | QA and closeout | Demobilization | $8,000.00 |
| 29 | Additional site works | Traffic control – quotation allowance | $25,000.00 |
| 30 | Additional site works | Utility relocation | $60,000.00 |
| 31 | Additional site works | Contaminated soil handling / disposal | $40,000.00 |
| 32 | Additional site works | In-water work allowance | $75,000.00 |
| 33 | Owner costs | Land acquisition / easements | $80,000.00 |
| 34 | Total direct project cost | $963,532.96 | |
| 35 | Contractor overhead & profit (15%, construction only) | $114,829.94 | |
| 36 | Subtotal before risk | $1,078,362.90 | |
| 37 | Contingency (25%) | $269,590.73 | |
| 38 | Escalation allowance (5%) | $67,397.68 | |
| 39 | Total capital cost before HST | $1,415,351.31 | |
| 40 | HST allowance (13%) | $183,995.67 | |
| 41 | TOTAL CAPITAL COST INCLUDING HST | $1,599,346.98 | |
| 42 | Low capital estimate before HST (75%) | $1,061,513.48 | |
| 43 | High capital estimate before HST (150%) | $2,123,026.97 | |
| 44 | Long-term maintenance (25-year allowance, before HST) | $150,000.00 | |
| 45 | TOTAL CAPITAL + MAINTENANCE (BEFORE HST) | $1,565,351.31 | |
Scroll to explore the worksheet. Use the zoom controls or Full screen to enlarge it. Press Esc to exit full screen.
Download original Excel (optional) ↓
Prefer to open the original in Excel?
Preliminary conceptual estimate · Not a contractor quotation.