PROJECT 02 / 01 / XLSXCONCEPTUAL DESIGN
Steel Truss Pedestrian Bridge

Construction cost estimate

Original Excel workbook containing the preliminary construction estimate and project cost assumptions.

Workbook / Original project file

Construction estimate workbook

Steel Truss Bridge Cost EstimateWORKSHEET 01 / READ-ONLY
100%
ABC
1STEEL TRUSS BRIDGE | COST ESTIMATE
2Conceptual pedestrian bridge • Ontario • CAD • Preliminary allowances
3
4Work packageCost itemEstimated cost
5PreconstructionSurvey and utility locating$9,000.00
6PreconstructionGeotechnical and environmental studies$24,000.00
7PreconstructionEngineering and approvals$45,000.00
8PreconstructionPermit and agency fees$7,000.00
9Site worksMobilization and site setup$28,000.00
10Site worksClearing and grading$12,250.00
11Site worksErosion and sediment controls$12,000.00
12Site worksExcavation and backfill$22,500.00
13Site worksTemporary access and dewatering$18,000.00
14SubstructureAbutments and foundations$170,000.00
15SubstructureBearings and anchor assemblies$18,000.00
16SubstructureDrainage and protection$18,000.00
17SuperstructureSteel material and shop fabrication$83,935.80
18SuperstructureProtective coating$16,787.16
19SuperstructureDeck system$32,400.00
20SuperstructurePedestrian railing$20,160.00
21SuperstructureTransport and delivery$15,000.00
22SuperstructureCrane and erection$35,000.00
23FinishingApproach pathways and transitions$40,000.00
24FinishingRestoration and landscaping$10,500.00
25FinishingSignage and site amenities$5,000.00
26QA and closeoutInspection and testing$15,000.00
27QA and closeoutContract administration and closeout$18,000.00
28QA and closeoutDemobilization$8,000.00
29Additional site worksTraffic control – quotation allowance$25,000.00
30Additional site worksUtility relocation$60,000.00
31Additional site worksContaminated soil handling / disposal$40,000.00
32Additional site worksIn-water work allowance$75,000.00
33Owner costsLand acquisition / easements$80,000.00
34Total direct project cost$963,532.96
35Contractor overhead & profit (15%, construction only)$114,829.94
36Subtotal before risk$1,078,362.90
37Contingency (25%)$269,590.73
38Escalation allowance (5%)$67,397.68
39Total capital cost before HST$1,415,351.31
40HST allowance (13%)$183,995.67
41TOTAL CAPITAL COST INCLUDING HST$1,599,346.98
42Low capital estimate before HST (75%)$1,061,513.48
43High capital estimate before HST (150%)$2,123,026.97
44Long-term maintenance (25-year allowance, before HST)$150,000.00
45TOTAL CAPITAL + MAINTENANCE (BEFORE HST)$1,565,351.31
Cost EstimateOriginal worksheet · 45 rows · CAD

Scroll to explore the worksheet. Use the zoom controls or Full screen to enlarge it. Press Esc to exit full screen.

Download original Excel (optional) ↓

Prefer to open the original in Excel?

Preliminary conceptual estimate · Not a contractor quotation.